The critical path of a network is
Answer: D
The critical path of a network is the longest time path through it, since the project cannot be completed in less time than the longest chain of activities. So (D) is the key. The shortest path in (B) is wrong because it would not fix the project time. Options (A) and (C) describe a zero slack on the activities of that path, and are the results of it, but they are not the definition of the path. A delay in an activity on that path delays the whole project, whereas activities not on it have slack. The path is found by a forward pass and a backward pass over the network.
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development