The ....................... is a plan for the production of individual end items.
Answer: D
The plan is the MPS, the master production schedule.
The master production schedule states which end items will be produced, in what quantities and in which periods. It translates the aggregate plan into a schedule for individual finished products and is the main input to MRP.
MRP (material requirements planning) works backwards from the MPS through the bill of materials to plan components and raw materials, not end items. MRP II extends this to all manufacturing resources, including capacity and finance. JIT is a philosophy of producing just what is needed when it is needed, not a schedule of end items.
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development