Arrange these availability targets from least to most demanding.
1. 99.95%
2. 99%
3. 99.99%
4. 99.9%

  • A.2 - 1 - 4 - 3
  • B.2 - 4 - 1 - 3
  • C.3 - 1 - 4 - 2
  • D.4 - 2 - 1 - 3

Answer: B

Correct answer: 2 - 4 - 1 - 3

Ordering by the permitted downtime rather than by the percentage makes the steps clear: 99 per cent allows about 7 hours a month, 99.9 about 43 minutes, 99.95 about 22 minutes and 99.99 about 4 minutes. Each additional nine costs roughly ten times as much engineering as the one before it, which is why the target should be chosen from what the business actually needs.