Match the allowance with what it covers.

1. Escalation   2. Contingency   3. Re-estimating

P. Uncertainty within the defined scope   Q. Price movement over the spending period   R. A change in the project's scope

  • A.1-Q, 2-R, 3-P
  • B.1-R, 2-P, 3-Q
  • C.1-Q, 2-P, 3-R
  • D.1-P, 2-Q, 3-R

Answer: C

Correct answer: 1-Q, 2-P, 3-R

Three allowances for three different uncertainties. Escalation covers price movement between the estimate and the spending. Contingency covers what is not yet known within the scope as defined. And a change to the scope itself is not an allowance at all - it requires the estimate to be redone, which is why contingency should never be treated as a fund for scope growth.