A utility avoids 100 MW of peaking capacity costing 40 million per MW. The capital deferred is
Answer: B
Correct answer: 4000 million
\[ 100 \times 40 = 4{,}000\ \mathrm{million}. \] The figure is a deferral rather than a saving outright, since the plant may still be needed later, but deferring capital for several years is worth a substantial fraction of its cost - and it is the avoided capacity, not the avoided energy, that usually justifies a demand side programme.
No comment is present. Be the first to comment.
Loading…
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development