Comparing an interruptible load contract with a peaking generator as a means of meeting a rare peak, the contract
Answer: B
A generator built for fifty hours a year carries its capital cost for all 8760, whereas the contract is paid a retainer and an energy rate only when used. Its reliability is generally lower than a generator's, which is the trade.