Arrange these conveyors in order of increasing product damage per tonne handled:
1. Screw conveyor
2. Belt conveyor
3. Pneumatic conveyor
4. Drag conveyor
Select the correct sequence.
Answer: A
A belt lets the material ride untouched, a drag moves it as a bed, a screw shears it against the trough and pneumatic conveying flings it against bends at high speed. The order is essentially the order of relative motion between grain and machine.
No comment is present. Be the first to comment.
Loading…
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development