A candidate part is available only from one distributor with a 40 week lead time. The correct conclusion for a product shipping in six months is
Answer: B
A part that cannot be bought is not a candidate, and forty weeks against a six month schedule is decisive. Availability belongs in the first screen alongside the peripheral set, as many designers learned during the shortages.