Work & Wages Questions and Answers

Important Instructions
1.

"A" can do a piece of work in 12 days. While "B" alone can do it in 15 days, with the help of "C" they can finish it in 5 days. If they are paid ₹ 960 for the whole work, what is the share of "A"?

Exam Year(s)

ISRO Assistant - 2023,

Answer: C

A's share is ₹ 400.

Payment is shared in proportion to the work each does. In the 5 days the work takes, A does 5/12 of it and B does 5/15 = 1/3:

\[ \begin{aligned} C &= 1 - \tfrac{5}{12} - \tfrac{4}{12} = \tfrac{3}{12} \\ A &: B : C = 5 : 4 : 3 \end{aligned} \]

A's share is \(960 \times 5/12 = 400\), with B getting 320 and C 240. Sharing by the ratio of days (12 : 15) instead of work done gives the wrong amounts.

Please log in or register to report this question.

2.

In a regular week, there are 5 working days and for each day, the working hours are 8. A man gets Rs. 2.40 per hour for regular work and Rs. 3.20 per hours for overtime. If he earns Rs. 432 in 4 weeks, then how many hours does he work for ?

Exam Year(s)

MPPSC State Service - 2022, MPPSC Forest Service - 2022,

Answer: B

He works 175 hours.

Regular hours in 4 weeks are 4 × 5 × 8 = 160. The earnings separate into regular pay and overtime:

\[ \begin{aligned} 160 \times 2.40 &= 384 \\ 432 - 384 &= 48 \\ 48 \div 3.20 &= 15 \text{ overtime hours} \end{aligned} \]

So he works 160 + 15 = 175 hours. 160 counts only the regular hours, and 180 and 195 would mean more overtime than Rs. 48 pays for.

Please log in or register to report this question.

3.

The daily wages of A and B respectively are ₹ 3.50 and ₹ 2.50. When A finishes a certain work, he gets a total wage of ₹ 63. When B does the same work, he gets a total wage of ₹ 75. If both of them do it together, what is the cost of the work ?

Exam Year(s)

Punjab Civil Service - 2025,

Answer: A

The cost is ₹ 67.50.

A takes \(\frac{63}{3.50} = 18\) days and B takes \(\frac{75}{2.50} = 30\) days to do the work alone. Together they do

\[ \begin{aligned} \frac{1}{18} + \frac{1}{30} &= \frac{5 + 3}{90} = \frac{8}{90} \\ \text{days} &= \frac{90}{8} = 11.25 \end{aligned} \]

Their combined daily wage is ₹ 6, so the cost is \(11.25 \times 6 = 67.50\). Averaging the two totals gives ₹ 69, and the other options do not follow from the times.

Please log in or register to report this question.

4.

Working alone A can do a task in 27 hours and B can do the same in 54 hours. Find C's share (in ₹) if A, B and C get paid ₹ 4,320 for completing a task in 12 hours on which they worked together.

Exam Year(s)

Punjab Civil Service - 2025,

Answer: A

C's share is 1,440 rupees.

In 12 hours A does \(\frac{12}{27} = \frac{4}{9}\) of the task and B does \(\frac{12}{54} = \frac{2}{9}\). C must do the rest:

\[ \begin{aligned} 1 - \tfrac{4}{9} - \tfrac{2}{9} &= \tfrac{3}{9} = \tfrac{1}{3} \\ \text{C's share} &= \tfrac{1}{3} \times 4320 = 1440 \end{aligned} \]

Payment is divided in proportion to work done. 1,920 is A's share and 960 B's.

Please log in or register to report this question.

5.

A can do a piece of work in 10 days and B can do it in 15 days. In how many days will they finish the work together?

Answer: B

Work in rates: someone who finishes a job in \( n \) days does \( \tfrac{1}{n} \) of it a day, and rates add.

\[ \frac{1}{10} + \frac{1}{15} = \frac{3 + 2}{30} = \frac{1}{6} \]

\[ t = 6 \text{ days} \]

Please log in or register to report this question.

6.

If A, B, and C can complete a piece of work in 12, 15, and 20 days respectively, in how many days can they together complete the work?

Answer: B

Total work can be assumed as the LCM of 12, 15, and 20, which is 60 units. A's efficiency = 60/12 = 5 units/day. B's efficiency = 60/15 = 4 units/day. C's efficiency = 60/20 = 3 units/day. Together, their efficiency = 5+4+3 = 12 units/day. Time taken to complete the work together = Total work / Combined efficiency = 60 / 12 = 5 days.

Please log in or register to report this question.

7.

A can do a job in 16 days, and B can do the same job in 12 days. With the help of C, they did the job in 4 days only. In how many days can C do the job alone?

Answer: A

Work done by (A+B+C) in 1 day = 1/4. Work done by A in 1 day = 1/16. Work done by B in 1 day = 1/12. Work done by C in 1 day = \(1/4 - (1/16 + 1/12) = 1/4 - (3+4)/48 = 1/4 - 7/48 = (12-7)/48 = 5/48\). So, C alone can do the work in 48/5 = 9.6 days.

Please log in or register to report this question.

8.

A and B are working on a job. A is twice as efficient as B. If A can finish the job in 30 days, in how many days can B finish the job alone?

Answer: C

Twice the efficiency means half the time, so B takes twice as long as A.

\[ 2 \times 30 = 60 \text{ days} \]

Please log in or register to report this question.

9.

Two pipes A and B can fill a tank in 20 and 30 minutes respectively. If both pipes are opened simultaneously, how long will it take to fill the tank?

Answer: B

Work in rates: someone who finishes a job in \( n \) days does \( \tfrac{1}{n} \) of it a day, and rates add.

\[ \frac{1}{20} + \frac{1}{30} = \frac{3 + 2}{60} = \frac{1}{12} \]

\[ t = 12 \text{ minutes} \]

Please log in or register to report this question.

10.

A works twice as fast as B. If both of them can together finish a work in 12 days, then in how many days can B alone do it?

Answer: D

Let the efficiency of B be x units/day. Then the efficiency of A is 2x units/day. Their combined efficiency is 3x units/day. Total work = Efficiency * Time = 3x * 12 = 36x units. Time taken by B alone = Total work / B's efficiency = 36x / x = 36 days.

Please log in or register to report this question.

Loading…
Tags: Work and Wages Questions and Answers || Work Efficiency MCQ Questions || Wages Problems GK || Quantitative Aptitude Work MCQ Questions || Work Time and Wages GK