Project implementation may involve many steps. Arrange those in sequential order by using codes given below :
(i) Initiating the project.
(ii) Clarifying authority, responsibility and relationships.
(iii) Directing and Controlling
(iv) Establishing Control System
(v) Obtaining resources
Codes :
UGC NET - 2013,
Answer: D
The steps of project implementation are: initiating the project, clarifying authority, responsibility and relationships, obtaining resources, establishing the control system, and directing and controlling (i, ii, v, iv and iii).
Resources must be obtained before the control system is set up, and directing and controlling follow once these are in place. Orders that put the control system before the resources, or directing before the system, are out of sequence.