21.

A completes 80% of a work in 20 days. Then B also joins and A and B together finish the remaining work in 3 days. How long would it take for B alone to complete the work?

Answer: B

A completes 80% (4/5) of the work in 20 days. So, A can complete the whole work in \(20 \times (5/4) = 25\) days. A's 1-day work is 1/25. Remaining work is 20% (1/5). A and B together finish 1/5 of the work in 3 days. So, their combined 1-day work is \((1/5)/3 = 1/15\). B's 1-day work = (A+B)'s work - A's work = \(1/15 - 1/25 = (5-3)/75 = 2/75\). So, B alone can do the work in 75/2 = 37.5 days.

Please log in or register to report this question.

22.

A and B can do a work in 12 days. B and C in 15 days. C and A in 20 days. How much time will A alone take to do it?

Answer: C

One day's work: A+B=1/12, B+C=1/15, C+A=1/20. Adding these three gives \(2(A+B+C) = 1/12 + 1/15 + 1/20 = (5+4+3)/60 = 12/60 = 1/5\). So, \(A+B+C = 1/10\). To find A's work, we subtract (B+C)'s work: \(A = (A+B+C) - (B+C) = 1/10 - 1/15 = (3-2)/30 = 1/30\). A alone will take 30 days.

Please log in or register to report this question.

23.

A tap can fill a cistern in 8 hours and another can empty it in 16 hours. If both are opened together, the time (in hours) to fill the tank is:

Answer: C

Work in rates: someone who finishes a job in \( n \) days does \( \tfrac{1}{n} \) of it a day, and rates add.

\[ \frac{1}{8} - \frac{1}{16} = \frac{2 - 1}{16} = \frac{1}{16} \]

\[ t = 16 \text{ hours} \]

Please log in or register to report this question.

24.

A is thrice as good a workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:

Answer: B

Let the time taken by A be T days. Then B takes 3T days. The difference in time is \(3T - T = 2T = 60\) days. So, \(T=30\). A takes 30 days and B takes 90 days. Their combined one day's work is \(1/30 + 1/90 = (3+1)/90 = 4/90 = 2/45\). So, together they will take 45/2 = 22.5 days.

Please log in or register to report this question.

25.

If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be:

Answer: A

Let 1 man's work = m, 1 boy's work = b. From the problem, \(10(6m+8b) = 2(26m+48b) \Rightarrow 60m+80b = 52m+96b \Rightarrow 8m=16b \Rightarrow m=2b\). Total work can be calculated from the first condition: \(10(6(2b)+8b) = 10(12b+8b) = 10(20b) = 200b\). We need time for 15 men and 20 boys. Their combined work rate is \(15m+20b = 15(2b)+20b = 30b+20b = 50b\). Time taken = Total work / Rate = 200b / 50b = 4 days.

Please log in or register to report this question.

26.

A contractor undertakes to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional men, how many days behind schedule would it be finished?

Answer: A

Let the work done by 1 man in 1 day be 1 unit. Total work = Work done in first 35 days + Work done in last 5 days = \(100 \times 35 + (100+100) \times 5 = 3500 + 200 \times 5 = 3500 + 1000 = 4500\) units. If the additional men were not engaged, the 100 men would have to do the entire work. Time taken = Total work / Number of men = 4500 / 100 = 45 days. The work would be finished 5 days behind the scheduled 40 days.

Please log in or register to report this question.

27.

Three men, four women and six children can complete a work in 7 days. A woman does double the work a man does and a child does half the work a man does. How many women alone can complete this work in 7 days?

Answer: A

Let a man's one day work be x. Then a woman's work is 2x and a child's work is x/2. Total work done in 1 day = \(3x + 4(2x) + 6(x/2) = 3x+8x+3x = 14x\). Total work = \(14x \times 7 = 98x\). We need to find how many women can complete this in 7 days. Let the number of women be W. Their one day's work is \(W \times 2x\). Total work done by them in 7 days = \(W \times 2x \times 7 = 14Wx\). Equating the total work: \(14Wx = 98x \Rightarrow 14W=98 \Rightarrow W=7\). So, 7 women are needed.

Please log in or register to report this question.

28.

A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in:

Answer: C

Let their 1 day's work be A, B, C. Given A = B+C. Also, A+B=1/10 and C=1/50. Substitute C in the first equation: A = B + 1/50. Substitute this A into the second equation: \((B+1/50) + B = 1/10 \Rightarrow 2B = 1/10 - 1/50 = (5-1)/50 = 4/50 = 2/25\). So, \(B = 1/25\). B alone can do the work in 25 days.

Please log in or register to report this question.

29.

A, B and C are employed to do a piece of work for Rs. 529. A and B together are supposed to do 19/23 of the work and B and C together 8/23 of the work. What amount should A be paid?

Answer: B

Wages are paid in proportion to the work done. Work done by (A+B) = 19/23. Work done by C = \(1 - 19/23 = 4/23\). Work done by (B+C) = 8/23. Work done by B = (B+C) - C = 8/23 - 4/23 = 4/23. Work done by A = (A+B) - B = 19/23 - 4/23 = 15/23. A's share = \((15/23) \times 529 = 15 \times 23 = 345\). A should be paid Rs. 345.

Please log in or register to report this question.

30.

A alone would take 27 hours more to complete a work than A and B together. B takes 3 hours more to complete a work alone than A and B together. In how many days can A alone do it?

Answer: B

Let the time taken by A and B together be x hours. Then A takes x+27 hours and B takes x+3 hours. Their combined one hour's work is \(\frac{1}{x+27} + \frac{1}{x+3} = \frac{1}{x}\). This gives \(x(x+3+x+27) = (x+27)(x+3) \Rightarrow x(2x+30) = x^2+30x+81 \Rightarrow 2x^2+30x = x^2+30x+81 \Rightarrow x^2=81 \Rightarrow x=9\). Time taken by A alone = x+27 = 9+27 = 36 hours.

Please log in or register to report this question.