A completes 80% of a work in 20 days. Then B also joins and A and B together finish the remaining work in 3 days. How long would it take for B alone to complete the work?
Answer: B
A completes 80% (4/5) of the work in 20 days. So, A can complete the whole work in \(20 \times (5/4) = 25\) days. A's 1-day work is 1/25. Remaining work is 20% (1/5). A and B together finish 1/5 of the work in 3 days. So, their combined 1-day work is \((1/5)/3 = 1/15\). B's 1-day work = (A+B)'s work - A's work = \(1/15 - 1/25 = (5-3)/75 = 2/75\). So, B alone can do the work in 75/2 = 37.5 days.
No comment is present. Be the first to comment.
Loading…
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development