A core run of 1.5 m yields intact pieces of 300, 250, 150, 120 and 80 mm. Its rock quality designation is
Answer: A
Correct answer: 55 per cent
Only pieces of 100 mm or more count, so the 80 mm piece is excluded:
\[ RQD = \frac{300 + 250 + 150 + 120}{1500} \times 100 = \frac{820}{1500} \times 100 \approx 55\% \]Including the 80 mm piece would give 60 per cent, which is the trap. Note also that total core recovery here is 900 of 1500 mm, a separate figure from the RQD.