A plant processes \( 9000 \) tonnes in a \( 90 \) day season working \( 20 \) hours a day. Its required capacity is

  • A.5.0 t/h
  • B.4.2 t/h
  • C.100 t/h
  • D.0.42 t/h

Answer: A

The daily rate is \( 9000/90 = 100 \) tonnes and the hourly rate is \( 100/20 = 5.0 \) tonnes. Sizing on the annual tonnage spread over a full year would give a plant less than a quarter of this and the crop would be lost.