Arrange the material's path through a well-laid-out fruit processing plant:
1. Reception and washing of raw material
2. Preparation, peeling and cutting
3. Thermal processing and filling
4. Packing, labelling and despatch
Select the correct sequence.
Answer: A
Correct answer: 1, 2, 3, 4
Reception and washing, then preparation, peeling and cutting, then thermal processing and filling, then packing and despatch. The sequence matters as much for hygiene as for logic: the material becomes progressively cleaner and more processed as it moves in one direction through the building, so raw and finished product never meet.
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development