A line rated at 6 t/h is found to deliver only 4.5 t/h, and material accumulates ahead of one machine.
What should be done first?
Answer: C
Correct answer: Uprate the limiting stage, then the next
The line is delivering the capacity of its slowest stage, and material accumulating in front of one machine identifies it. Uprate that one, then look again - the next slowest becomes the constraint, and debottlenecking proceeds one stage at a time. Uprating everything equally would spend far more for the same result.
No comment is present. Be the first to comment.
Loading…
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development