Discussion
A vehicle starts poorly each morning, the battery tests as sound after charging, and a parasitic drain of 400 milliamps is measured after the modules have slept.
Which conclusion follows?
Answer: A
Four hundred milliamps is roughly ten times the acceptable figure and will flatten a battery in a few days. The battery itself has tested sound. Fuse by fuse investigation identifies the circuit responsible. The shared behaviour explains why these belong together and the differences explain why both exist. Tracing the requirement back to the physical constraint that produces it makes the answer follow. Reading the definition literally, rather than recalling a summary, avoids the usual confusion.
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development