A project is acceptable if its benefit cost ratio is
Answer: D
Correct answer: at least one
A ratio of one means the discounted benefits net of disbenefits exactly equal the discounted costs, so the project just earns the discount rate. Above one it is worth doing; below one it is not. The discount rate is already inside the calculation, which is why the criterion is unity rather than the rate itself.