Double counting occurs in a benefit cost study when the same effect is counted
Answer: C
Correct answer: as a benefit and again as a cost saving
The classic case is counting both the time road users save and the resulting rise in land values, when the second is largely the capitalisation of the first. Counting both inflates the numerator without any additional real effect, and it is one of the commonest ways an appraisal is made to pass.
No comment is present. Be the first to comment.
Loading…
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development