The with-and-without principle requires benefits to be measured as the difference between the situation with the project and

  • A.the situation before it
  • B.the best alternative project
  • C.a hypothetical ideal project
  • D.the situation without it

Answer: D

The comparison is against what would have happened anyway, which is not the same as the situation before construction, since conditions would have changed regardless. Using the before-and-after difference credits the project with changes it did not cause.