For that project the benefit cost ratio is about
Answer: B
Dividing 250 000 of annual benefit by 203 700 of annualised cost gives 1.227. The project is acceptable at 8 per cent, though not by a wide margin, so the discount rate assumed will matter a great deal to the conclusion.