Discussion
A man completes \(\frac{5}{8}\) of a job in 10 days. At this rate, how many more days will it take him to finish the job ?
Answer: B
Find the daily rate first, then apply it to what is left. Completing \( \tfrac{5}{8} \) in 10 days means
\[ \text{rate} = \frac{5/8}{10} = \frac{1}{16} \text{ of the job per day} \]
The remaining fraction is \( 1 - \tfrac{5}{8} = \tfrac{3}{8} \), so
\[ \text{days} = \frac{3/8}{1/16} = \frac{3}{8} \times 16 = 6 \]
The question asks how many more days, so 6 is the answer; 16 would be the total time for the whole job from the start.
No comment is present. Be the first to comment.
Loading…
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development