A certain number of men can finish a piece of work in 100 days. If there were 10 men less, it would take 10 days more for the work to be finished. How many men were there originally?
Answer: D
The total work in man-days is fixed.
\[ 100M = 110(M - 10) \]
\[ 100M = 110M - 1100 \quad\Longrightarrow\quad 10M = 1100 \]
\[ M = 110 \]