A certain number of men can finish a piece of work in 100 days. If there were 10 men less, it would take 10 days more for the work to be finished. How many men were there originally?

   
   

  • A.75
  • B.82
  • C.100
  • D.110

Answer: D

The total work in man-days is fixed.

\[ 100M = 110(M - 10) \]

\[ 100M = 110M - 1100 \quad\Longrightarrow\quad 10M = 1100 \]

\[ M = 110 \]