If 560 workers can complete a project of constructing a bridge in 7 months, then how many more workers will be required to complete the same project in 5 months?

  • A.400
  • B.408
  • C.784
  • D.224

Answer: D

224 more workers are needed. The work is 560 × 7 = 3920 worker-months. In 5 months the workers needed are 3920 / 5 = 784. The extra workers are 784 - 560 = 224.

784 is the total required, not the extra, and 400 and 408 do not come from the inverse proportion.