Arrange the steps of choosing a deployment model in order.
1. compare candidate models against those requirements
2. identify regulatory and data residency constraints
3. plan the exit route before committing
4. characterise the workload's demand pattern and latency needs

  • A.3 - 1 - 4 - 2
  • B.4 - 2 - 1 - 3
  • C.2 - 1 - 4 - 3
  • D.2 - 4 - 1 - 3

Answer: D

Correct answer: 2 - 4 - 1 - 3

The constraints come first because they are non-negotiable and may eliminate whole options before anything else is considered. The workload’s demand pattern and latency needs follow, since they determine what would suit. Only then can candidate models be compared against both. Planning the exit route comes last but before committing - it is far cheaper to design while the choice is still open than to discover later that there is no way back.

No comment is present. Be the first to comment.
Loading…

Post your comment

Please log in or register to post a comment.