Construction of a rubble mound in exposed conditions is usually limited by
Answer: C
Partly built structures are far more vulnerable than completed ones to a storm. Construction risk is managed by sequencing the work so that the exposed states are as brief as possible. Sequencing is part of the design, not an afterthought.