Arrange the construction stages of a rubble mound breakwater in order.
1. placing the primary armour on the underlayer
2. placing the core material from the advancing end
3. casting the crown wall along the finished crest
4. placing the underlayer over the exposed core
Answer: B
Correct answer: 2 - 4 - 1 - 3
The mound is built from the inside outward and from the bottom up. Core material is placed first, usually end-tipped from an advancing haul road; the underlayer follows over the exposed core, protecting it from washout; the primary armour is placed on the underlayer; and the crown wall is cast last, along the finished crest. Placing armour before the underlayer would leave the core to be lost through the voids.
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development