Consider the following statements about stakeholder engagement.
1. Early engagement identifies objections while options remain open.
2. Late engagement tends to entrench opposition to a fixed proposal.
3. Engagement is best deferred until the design is complete.

  • A.1 and 2 only
  • B.3 only
  • C.1 only
  • D.All of them

Answer: A

The first two are correct and are why engagement begins early. The third describes the approach that most reliably produces conflict and delay. People distinguish consultation from notification. Being informed is not the same as being heard.