Machine-translated by Google. Questions are authored in English.
Top

Discussion

Match each instrument with what it does.
List I
A. Environmental impact assessment
B. Habitats assessment
C. Marine licence
D. Planning permission
List II
1. permits works in the marine area
2. identifies effects before consent
3. permits development on the land side
4. tests effects on designated sites

  • A.A-3, B-1, C-4, D-2
  • B.A-2, B-4, C-1, D-3
  • C.A-4, B-2, C-1, D-3
  • D.A-2, B-4, C-3, D-1

Answer: B

Correct answer: A-2, B-4, C-1, D-3

Four instruments, four jobs. Environmental impact assessment identifies significant effects before the decision is taken. Habitats assessment is the narrower and more demanding test applied where a designated site may be affected. A marine licence permits works below the tideline; planning permission permits development above it. A coastal scheme crossing the shoreline generally needs both.