The cost committed by the end of conceptual design is
Answer: C
Correct answer: Most of the total, though little is spent
By the end of conceptual design perhaps five per cent of the programme budget has been spent, but the configuration chosen - number of engines, layout, materials, technology level - determines something like two thirds of the lifetime cost of development, manufacture and support. Later phases refine within those choices rather than reopening them. This mismatch between spend and commitment is why so much analytical effort is justified so early, when changes are still nearly free.
No comment is present. Be the first to comment.
Loading…
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development