A design uses three technologies at readiness levels \( 5, 4 \) and \( 6 \), where \( 6 \) is required. The number needing maturation work is
Answer: C
Correct answer: 2
Two of the three technologies sit at levels 5 and 4, below the level 6 required, so both need maturation work; the third is already at 6. Counting them explicitly is the point of recording readiness levels: a design may quietly accumulate several immature technologies, each individually defensible, whose combined risk nobody has added up until the programme is committed.
No comment is present. Be the first to comment.
Loading…
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development