Consider the following statements about cost commitment:
1. Most lifetime cost is committed during conceptual design.
2. Very little of the budget is spent at that stage.
3. Cost reduction efforts are most effective during detail design.
Which of the statements given above is or are correct?
Answer: B
The first two are correct and together make the case for investing in early design. The third follows the money rather than the leverage: by detail design most of the cost is already committed and little remains genuinely open.
No comment is present. Be the first to comment.
Loading…
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development