Match each practice in List I with the problem it addresses in List II.

List I

A. Concurrent engineering

B. Digital mock-up

C. Design review gate

D. Recording technology readiness

List II

1. Clashes and access found only at assembly

2. Designs that cannot be built or maintained economically

3. Unrecorded accumulation of immature technology risk

4. Committing a large workforce to an unproven configuration

Select the correct match.

  • A.A-3, B-1, C-4, D-2
  • B.A-2, B-1, C-4, D-3
  • C.A-1, B-2, C-4, D-3
  • D.A-2, B-4, C-1, D-3

Answer: B

Correct answer: A-2, B-1, C-4, D-3

Concurrent engineering brings manufacturing and support into the design team so that unbuildable or unmaintainable designs are caught while they can still be changed. A digital mock-up finds clashes and access problems that would otherwise appear at first assembly. A design review gate prevents a large workforce being committed to an unproven configuration. Recording technology readiness prevents the silent accumulation of immature technology risk.