Discussion
.................. procedures are concerned with analysing the costs and benefits of proposed changes, approving those changes that are worthwhile and tracking which components of the system have been changed.
Answer: A
These are change management procedures.
Change management analyses the costs and benefits of proposed changes, approves those that are worthwhile and tracks which components of the system have been changed, so that evolution is controlled and documented.
Cost estimation predicts the effort and cost of development, testing checks the software for defects, and 'software' is not a procedure at all. None of them covers approving and tracking changes.
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development