Machine-translated by Google. Questions are authored in English.
Top

Discussion

Spreading RDT&E over a larger production quantity

  • A.Increases the unit production cost
  • B.Has no effect on unit price
  • C.Increases the total programme cost
  • D.Reduces amortised development cost

Answer: D

Correct answer: Reduces amortised development cost

RDT&E is a one-off expense incurred before the first delivery, so dividing it over more aircraft reduces the share each must carry:

\[ \text{amortised cost} = \frac{\text{RDT\&E}}{N} \]

A \( 2.4 \) billion dollar development spread over 300 aircraft adds 8 million dollars each; over 600 it adds only 4 million. The total programme cost rises with quantity because more aircraft are built, but the unit production cost falls through learning as well, so both effects push unit cost down as the run lengthens.

No comment is present. Be the first to comment.
Loading…

Post your comment

Please log in or register to post a comment.