An order of magnitude estimate is prepared to an accuracy of roughly
Answer: A
It is made from capacity figures and past projects before any engineering has been done, so it serves only to decide whether an idea is worth pursuing further. Committing funds on such a figure is how projects come to overrun, since the estimate was never intended to bear that weight.