A definitive estimate is distinguished from a preliminary one by resting on

  • A.an index adjustment of an older figure
  • B.completed engineering and firm quotations
  • C.capacity scaling from a similar plant
  • D.a single cost per unit of output

Answer: B

Detailed drawings, bills of quantities and supplier prices bring the accuracy to within a few per cent, which is what a contract award requires. The work needed to produce it is itself substantial, so it is prepared only once the project is likely to proceed.