A parametric or cost estimating relationship expresses cost as a function of
Answer: A
Cost per megawatt, per square metre or per tonne of throughput is derived by regression from past projects and then applied to the new one. Its value depends entirely on the new project resembling those in the sample, which is a judgement the arithmetic cannot make.