Discussion

A detailed or bottom-up estimate builds the total from

  • A.an index adjustment of a past total
  • B.a factor applied to the equipment cost
  • C.priced quantities of each item of work
  • D.a single cost per unit of capacity

Answer: C

Every item is measured, priced and summed, which is the most accurate approach and by far the most laborious. It cannot be attempted until the design is essentially complete, which is why the earlier classes of estimate exist at all.