The unit rate method estimates cost by multiplying a measured quantity by
Answer: D
Rates per cubic metre of concrete or per metre of pipe are held in a schedule and applied to the quantities taken off. It sits between analogy and full detail in both effort and accuracy, and is the workhorse of construction estimating.
No comment is present. Be the first to comment.