The critical path method is a/an ______ oriented technique, which is used in project management.

  • A.activity
  • B.event
  • C.time
  • D.resource

Answer: A

The critical path method (CPM) is an activity-oriented technique: the network is drawn with arrows representing the activities, and the critical path is the longest chain of activities. PERT, in contrast, is an event-oriented technique, in which the nodes are events and the times are probabilistic. CPM is not oriented to time or to resource as such, although it gives time results (the project duration and the float), and resource levelling is a later step.