Discussion
The probability distribution taken to represent completion time in PERT analysis is:
Answer: C
PERT represents activity completion time by a Beta distribution.
PERT assumes each activity time follows a beta distribution, which is bounded by the optimistic and pessimistic times and can be skewed either way. That assumption is what gives the formulas te = (to + 4tm + tp)/6 and σ = (tp - to)/6.
The normal distribution is the trap: it is used for the project completion time, which by the central limit theorem is roughly normal when many activities are added, not for a single activity. Gamma and log-normal are not the PERT assumption.
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development