Suppose there are 5 processes P1, P2, P3, P4 and P5 with processing time requirements 10, 6, 2, 4 and 8 respectively. What is the average completion time if SJF (Shortest Job First) policy is used ?

  • A.10
  • B.12
  • C.14
  • D.16

Answer: C

The average completion time is 14.

SJF runs the jobs in increasing order of time: 2, 4, 6, 8, 10 (P3, P4, P2, P5, P1). Each job completes when all the jobs before it and itself have run.

\[ \begin{aligned} \text{completions} &= 2, 6, 12, 20, 30 \\ \text{average} &= \frac{70}{5} = 14 \end{aligned} \]

The average waiting time is \((0+2+6+12+20)/5 = 8\), which is not offered; 10 is simply the longest job, and 12 and 16 match neither measure. The question asks for completion (turnaround) time with all jobs arriving at 0.