The avoided cost against which a demand side programme is evaluated is the cost the utility

  • A.recovers from the participating consumers
  • B.would incur in purchasing the equipment that has been installed
  • C.would have incurred to supply the energy and capacity saved
  • D.actually incurs in running the programme

Answer: C

Deferred generation, transmission and distribution investment together with the avoided fuel is what the programme is worth to the system, and the programme is worthwhile if it costs less than that. Estimating it is the central difficulty of the appraisal.