Requirements creep describes

  • A.The failure to write requirements at all
  • B.The process of verifying requirements
  • C.Gradual accumulation of extra requirements
  • D.The reduction of requirements over time

Answer: C

Correct answer: Gradual accumulation of extra requirements

Requirements creep is the steady addition of further requirements after the specification is agreed, each defensible on its own and each carrying a little weight, cost or schedule. The difficulty is that nobody sees the total until it is large. The remedy is formal change control, in which every proposed addition is costed in weight, performance and schedule before it is accepted.