Assertion (A): Design margin is allocated and tracked explicitly from the start of a programme.
Reason (R): Weight and performance almost always deteriorate as detail design proceeds.
Select the correct answer from the options below.
Answer: A
Correct answer: Both A and R are true, and R is the correct explanation of A
Both are true and the reason is why the practice exists. Weight grows and performance erodes as detail design uncovers what the concept estimate missed - brackets, fasteners, wiring, access provisions. A margin allocated and tracked from the start absorbs that growth, and tracking it makes the consumption visible while there is still time to act. Margin that is merely assumed is invariably found to have been spent already.
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development