Consider the following statements about programme risk:

1. A risk register records likelihood, impact and mitigation.

2. Low technology readiness at design freeze is a schedule risk.

3. Recording a risk is sufficient to manage it.

Which of the statements given above is or are correct?

  • A.2 and 3 only
  • B.1, 2 and 3
  • C.1 and 2 only
  • D.1 and 3 only

Answer: C

Correct answer: 1 and 2 only

Statements 1 and 2 are correct. Statement 3 is the failure mode of risk management: a register that is written and then filed changes nothing. A risk is managed only when someone owns it, a mitigation is funded and scheduled, the residual likelihood and impact are reassessed as work proceeds, and a trigger point is agreed at which the fallback is invoked.