Consider the following statements about programme risk:
1. A risk register records likelihood, impact and mitigation.
2. Low technology readiness at design freeze is a schedule risk.
3. Recording a risk is sufficient to manage it.
Which of the statements given above is or are correct?
Answer: C
Correct answer: 1 and 2 only
Statements 1 and 2 are correct. Statement 3 is the failure mode of risk management: a register that is written and then filed changes nothing. A risk is managed only when someone owns it, a mitigation is funded and scheduled, the residual likelihood and impact are reassessed as work proceeds, and a trigger point is agreed at which the fallback is invoked.
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development