Assertion: a project with a negative net present value loses money. Reason: its benefits are worth less than its costs in present terms.
Answer: D
In present terms the benefits are indeed the smaller, which is what the negative value states, but the project may still return more than it cost in absolute money. What it fails to do is beat the return the capital could earn elsewhere, which is a different and weaker charge.