None of the following belongs in a life cycle cost comparison except

  • A.the tariff paid in the year before the project
  • B.the maintenance cost over the equipment's life
  • C.the auditor's fee for identifying the measure
  • D.the depreciation of unrelated plant on the site

Answer: B

Maintenance persists for the whole life and may differ between the options, so it belongs alongside capital and energy. The audit fee is a sunk cost, and the other two have nothing to do with the choice between the alternatives.