A site's power factor is 0.99 and its bill still shows a large demand charge. The measure to pursue is
Answer: C
Correct answer: reducing or staggering the coincident peak
At 0.99 the power factor is already as good as it needs to be, so more capacitors would achieve nothing and could push it leading. A large demand charge with a good power factor means the site genuinely draws a high peak, and the only remedy is to lower that peak - by staggering starts, shifting batch processes, or shedding non-essential load when the demand approaches its target.
No comment is present. Be the first to comment.
Loading…
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development